Why unit 6?

To cut the cost price of electrical energy, reduce negative influences on the environment:

SO2 from 400 to 100 mg/Nm,
NOx from 500 to 150 mg/Nm3,
CO2 by 35% per MWh,
reduce the amount of dust particles, lower the noise level ...

Unit 6 will also enable us to extend the production of electrical energy, determined by the amount of coal in the Premogovnik Velenje mine, from 2025 to 2054.

Technical charasteristics of unit 6
1. Unit 6 net power 545,5 MW
2. Specific net consumption 8.451 kJ/kWh
3. Price of coal 2,75 EUR/GJ
4. Hours of operation at full power 6.500 h/year
5. Number of employees 200
6. Service life 40 years
7. CO2 emissions 0,87 kg/kWh
8. operating permit February 2016